![]() Sporadically and at varying levels of effort. However, your projects mayĬontain activities for which you know work will be performed Hours, Week 3 – 20 hours, Week 4 – 20 hours. ForĮxample, a four-week activity with 80 budgeted units is spread asįollows, assuming a weekly timescale: Week 1 – 20hours, Week 2 – 20 Units for an assignment to that activity are spread evenly across theĭuration of the activity, in the timescale increment you choose. The term "bucket" is generally used in future periodīucket planning, which enables you to manually enter and edit assignmentĪns : When you specify an activity's total budgeted units, the budgeted You can view, enter, and edit activity and assignment data in variousīuckets, such as daily, weekly, monthly, quarterly, yearly, andįinancial period. A bucket is another term for "timeperiod." In Primavera applications,